By Rosalie C. Periabras | The Manila Times | September 10, 2015

The Department of Transportation and Communications (DOTC) and the MRT-3 project team are heading for Dalian in China next week to meet with the German suppliers of traction systems, gearboxes, and brake systems.

 “As we announced last June, static testing will be conducted from September to October. Meanwhile, dynamic testing was scheduled from November to December, when these parts will be delivered from Germany,” DOTC Secretary Emilio Joseph Abaya.

“To fast-track the whole process, we met with officials from the German Embassy, Voith, and Knorr-Bremse a few weeks back regarding delivery schedules. Next week, our team will discuss the details with these suppliers, so we can explore ways to provide more trains to the public earlier than scheduled,” Abaya explained.

Voith will manufacture the traction systems and gearboxes for the 48 brand new coaches of the Metro Rail Transit Line 3 (MRT-3), while Knorr-Bremse is in charge of the brake systems. Both firms are major industry players.

Maintenance provider

The DOTC is targeting to award the P4.25-billion contract for a three-year maintenance provider in the fourth quarter of the year and take over by January 2016 the respective works given to seven multi-discipline contractors currently maintaining the rail line.

The long-term maintenance provider will not only undertake the regular maintenance of the system over the next three years, it will also conduct the general overhaul of existing MRT-3 coaches and replace the signaling system.

The general overhaul is needed to improve the condition of the 16-year old coaches, and replacing the signaling system will ensure safer operations for the line.

The emergency mode of negotiated procurement for the maintenance provider was approved by the Government Procurement Policy Board (GPPB), the Department of Justice (DOJ), and the National Economic Development Authority (NEDA) as an urgent need to address core problems of obsolescence and wear-and-tear.

The government also stepped in to perform improvement works on the privately-owned MRT-3 system.

The DOTC has already procured over 7,000 linear meters of new rails which will be used to replace worn-out tracks starting in the fourth quarter of the year. The rehabilitation of escalators and elevators, and the refurbishment of toilet facilities, are presently ongoing.


Latest News

September 4, 2023

MANILA - Manuel V. Pangilinan -led Metro Pacific Investments Corp. joined forces with...

August 19, 2023

MANILA, Philippines €” A commuter's group is calling on authorities to consider extending...

August 17, 2023

MANILA, Philippines €” The management of the Metro Rail Transit Line 3 (MRT-3) on Thursday...

August 4, 2023

MANILA €“ The Metro Rail Transit-3 (MRT-3) is ready to accommodate commuters who will be...




August 1, 2023

MANILA -- Blind and visually-impaired passengers can get free rides on the MRT-3 from August 1...

July 31, 2023

MANILA, Philippines €” The Department of Transportation (DOTr) has until July 2024 to decide...

July 15, 2023

The 48 sets of Dalian trains procured by the Philippine government to expand the operations of...

July 3, 2023

The operator of the Metro Rail Transit Line 3 (MRT3) has filed a petition to hike its fares, as...

View More Stories